Overlay Project Schedule for "A" Street

The City of Altus will be working with Hokett Construction to complete a street asphalt overlay project from the 100 block of “A” Street to the block of Ash Street. The overlay project will be completed in increments. The roads will be closed daily but will be re-opened for travel in the evenings. Work is scheduled to begin on Monday, September 11.


Estimated Overlay Schedule for “A” Street:


Mon, Sept. 11: 200 to 500 block of “A” Street

Tues, Sept. 12: 500 to 800 block of “A” Street

Wed, Sept 13: 800 to 1000 block of “A” Street

Thurs, Sept 14: 1 block of Ash Street


The Street Department appreciates residents and businesses cooperation during the project. For any questions or concerns please contact the City of Altus Street Department at (580) 481- 2224.